Project Description
Client: Local
Location: Lincoln Way West and Charles Martin Redevelopment
Year Completed: 2018
Selge performed the total reconstruction of the Lincoln Way West, Charles Martin, and Leland intersection. The main goal of the project was to improve the traffic flow and develop the surrounding area in a way that would promote better business and residential flow. Selge installed:
- (1000’) 12” Sanitary Sewer PVC Pipe
- (20) Sanitary Sewer Manholes
- New Bike racks
- New fire hydrants
- All new asphalt roads and concrete sidewalks
- All new street lighting and landscaping
- Brick paving